VicRoads
Budget
~ $250,000
Services Rendered
Type of Service: Field Investigation / Technical Services Contract
Services Provided: Material analysis, quality control testing & associated works
Deliverables
- Perform 9 Investigative Boreholes to a max depth of 25m
- Undergo 219 Pavement investigation test pits
- Preliminary materials testing for design and construct
- CBR, Atterberg, Particle Size, Point Load testing
M80 Upgrade Design Project
M80 Geotechnical investigation for the M80 upgrade project. consisting of 216 test pits, 9 boreholes and associated laboratory testing The M80 Ring Road Upgrade is a $2.25 billion project, jointly funded by the Victorian and Australian governments. The M80 Ring Road Upgrade is a 38km Western and Metropolitan Ring Roads, from Princes Hwy at Laverton North to the Greensborough Hwy at Greensborough.